May 2009 - Project Work Continues
5/27
New Addition:
-Begin roofing at sloped and high flat areas
-Continue with placement of stone at porte-cochere
-Finish sheathing on trusses
-Set windows at available openings
- Column framing at first and second levels
Remodeling:
-Begin setting doors at lower level
-Offices on lower level and second level to be prepped
Back Parking Lot to Remain Closed Through Project
Although the parking lot has been resurfaced with one layer of asphalt, it will not be open for parking until the end of the project. In the spring, another layer of asphalt will be applied.
5/17
New Addition:
-Finish stone on high west wall
-Set trusses at west wall
-Start upper rubber roof at Nave
-Start tile at restrooms in new addition (both 1st and 2nd levels)
Remodeling:
-Work on music room bulkheads and ceiling grid
-Drywall enclosure for ductwork out of Diane’s office
-Finish drywall at air handling unit behind theater
-Continue with elevator installation
5/10
New Addition:
-Placement of exterior stone continues
-Drywall continues and tile begins in new addition restrooms
-Elevator work continues
-Brooks Construction to start concrete work at west end of lot (weather permitting)
Remodeling:
-Wagenhals area cleaned up and turned over to church by end of week
-Demolition of Drama Director's office behind theater
-Drywall at the air handling unit behind theater (pending city inspections)
-Demolition openings at the 2nd level
5/3
New Addition:
-Complete structural fix at stone lintels on west end
-continue with stone at exterior
-set windows on east end where masons are complete
-drywall restrooms in new addition on both 1st and 2nd levels
Remodeling:
-finish ceilings at lower level where needed
-drywall @ AHU #2 area
-paint/drywall mud @ work room area
-demo @ window/opening 2nd level near secretary area
-elevator company mobilize on jobsite this week
-
April 2009 - Project Work Continues
4/26
New Addition:
• Finish trusses of east gable
• Finish sheathing on east trusses
• Continue with stonework on new addition
• Installation of windows in mechanical room
• Blocking on second level windows
• Tyvek for exterior walls
• Finish tile work in men's and family restrooms in Wagenhals Hall area
Remodeling:
• Drywall mud and paint in corridor outside brides room
• Ceiling work in corridor outside bride's room
• Ceiling work in men's robing room
• Ceiling work outside theatre at bulkhead
• Finish AHU # 2 at west side, lower level
• Begin ceiling work in men's and family restrooms by Wagenhals Hall area
4/19
New Addition:
• Continue with stone at upper high south wall
• Structural bracing at T-5 trusses (west trusses)
• Install windows at mechanical room openings
• Trusses/sheathing at east truss
• Finish framing bulkheads at 1st Level
• Roof penetration for sheet metal/ductwork complete
Remodeling:
• Drywall finishes at lower level (Bride’s Room area) and at AHU #2 area (behind the theater)
• Ceiling started at Bride’s Room area in corridor
4/12
New Addition:
• Start metal shingles
• Complete sheathing at trusses
• Complete trusses
• Complete densglass at exterior
• Stone work on exterior continues
Remodeling:
• Toilet accessories/fixtures in men’s restroom
• Plaster patch on lower level
• Paint corridor by new elevator
• Continue carpet removal on lower level
4/5
New Addition:
• Continue with stone at lintels
• Continue to set trusses in available areas
• Continue sheathing on trusses
• Rubber roof modifications at lintel areas
• Metal studs at concrete/steel columns
• Drywall in restrooms
• Sprinkler system installed
Remodeling:
• Start tile work in men’s restroom
• Possible carpet removal in lower level
• Start demolition for new openings on 2nd level
- March 2009 - Project Work Continues
3/29
New Addition:
• Continue with joists/plywood on high roof at Nave area
• Structural steel amendments on site and fabricated
• Mason work begins on stone at lintels
• Blocking at exterior windows on 2nd level
• Trusses set above mechanical room (weather permitting)
• Densglass at exterior (where available)
• Sheathing started on trusses
Remodeling:
• Finish acoustical ceiling at women’s and men’s robing, corridor, and TCC
• Begin ceiling at new corridor by kitchen
• Begin new stone work at corridor opening by kitchen
• Mud, tape, and paint men’s restroom by Wagenhals Hall
3/22
Remodeling:
• Start finishing work in restrooms by Wagenhals Hall (i.e. drywall taping, mudding, and painting)
• Start ceiling patch in kitchen area (by old elevator shaft )
• Low voltage wiring/re-routing continues
New Addition:
• Continue with exterior stone work
• Continue with truss installation
• Continue with roof sheathing
• Exterior glass installation
• Potentially begin metal stud column wraps on 1st floor
3/15
Remodeling:
• Complete rough-in at men’s restroom/inspection completed
• Blocking at restroom areas for toilet accessories
• Low voltage wiring and re-routing continues
• Drywall in men’s restroom walls only
New Addition:
• Trusses started on 2nd level
• Joists/plywood on roof started
• Stone work continues on exterior
• Mechanical room work continues
3/8
New Addition:
• Finish structural steel erection
• Begin metal stud work on 2nd level exterior
• Delivery of metal trusses
• Demolition work for 1st level kitchen
• Stonework continues on Mechanical Room
• Mechanical work continues
• Start low sloped roof joists/sheeting
Remodeling:
• Drywall started in Wagenhals’ restrooms
• Plumbing and electrical in Wagenhals’
• Demolition for sheet metal duct work at 2nd level
• Possible drywall at men’s restroom by Wagenhals’
• Acoustical ceiling at corridor/TCC
• Low voltage wiring at lower level continues
3/1
New Addition:
• Structural steel set on second level
• Temporarily enclose/block first level
• Work continues on mechanical room
• Delivery of limestone and/or stone
• Metal stud work for new restroom area
• Fix temporary roof for mechanical room
Remodeling:
• Metal stud work for new restroom area (Wagenhals Hall area)
• Paint corridor and janitor’s closet in lower level
• Begin low voltage wiring of lower level
• AHU started for heat for lower level
- February 2009 - Project Work Continues
2/22
Wagenhals Hall closes and will be used as a staging area for construction work for the next 8-10 weeks. The restrooms are under construction and temporarily closed. Additional restrooms are available outside Pastor Hasecke’s office; also, on the west end, second floor of Education Wing; in Pastor Haller’s office, between the stairs and exit on west side of Nave; outside Room 102; in room 105 (nursery); east of the Music Room in lower level; and just west of the Youth Center.
2/15
Outside:
• Finish the 2nd level form work
• Installation of steel studs and drywall on exterior of new addition
• Steel erection week of Feb. 16th
• Preparation of light poles for installation
• Electrical and plumbing work continues in mechanical room
Inside:
• Lower level restrooms available
• Wagenhals Hall demolition begins
• Music corridor ceiling removal
2/8
Outside:
• Bracing and concrete forms removed from under second floor
• New transformer set and power transfer complete
• Set up of mechanical equipment in new Mechanical Room.
• Begin placement of exterior studs
Inside:
• Waiting on delivery of new air-handler for east wing
2/1
New Addition:
• Start removing form work and shoring from deck (pending concrete test)
• Form up mechanical pads and pour in mechanical rooms
• Begin to demobilize equipment and material
• Plumbing and electrical work continues in mechanical rooms
• Layout, drill, core, and epoxy bolts on 2nd level deck
Remodel Area:
• Tile restrooms
• Finish ceiling grid and pads at all accessible locations in lower level
• Install toilet accessories and fixtures in restrooms
• General clean up of lower level
• Start plaster patches for several locations on lower level
- January 2009 - Project Work Continues
1/25
New Addition:
• Pour second level concrete deck (weather permitting)
• Electrical, plumbing, and temporary roof work for mechanical room
Remodel Work — lower level restrooms and youth center area
• Continue drywall finishing in all areas
• Paint primer on drywall
• Continue work on acoustical ceilings
• Continue work in restrooms
• Install sink/piping at youth center bar area
• Route and re-route electrical, including wire termination in electrical boxes
1/11
Lower Level:
• Drywall various areas
• Continue work on restrooms
Library:
• Drywall around new duct work
Mechanical Room:
• Pour concrete for second floor
• Construct temporary roof for electrical work to progress
-
December 2008 - Project Work Continues
12/21
• Relocate organ blower
• Saw cut outside concrete slab
• Form deck for second floor
• Masons continue to install blocks for elevator and mechanical room
• Set structural steel for mechanical room
• Set up metal sheet work and drywall on lower level
• Continue clean-up in lower level
12/14
• Grade, stone, and asphalt east parking lot
• Backfilling at foundation walls
• Construct block walls for the elevator shaft in the basement and first floor
• Construct block walls for the mechanical room
• Placement of underground sanitary sewer system
• Running power to the site lighting and building lighting
• Begin framing for interior walls
• Continued work on heating, ventilation and air conditioning (HVAC)
12/7
• Placement of underground ductwork continues
• Grading and asphalting of east parking lot
• Concrete slab will be poured for first level
• Electrical connections in parking lot and concrete slab (first level), and lines re-routed
• Demolition begins outside Theater hallway
• General clean-up in lower level
-
November 2008 - Project Work Continues
11/30
• Move trailers, materials and equipment to west parking lot
• Demolition of asphalt on east lot
• Underground plumbing and ductwork for new addition
• Mason work begins, starting with elevator shaft
• Pour mechanical room floor
11/23
• Asphalt on Washington parking lot
• Masons mobilized and will start on elevator shaft
• Underground plumbing beginning from new mechanical room going east
• Underground ductwork will follow the plumbing
11/16
• Complete exterior wall pouring
• Form/pour slab on grade for underground ductwork
• Stone and asphalt on 1/2 of new parking lot
• Backfill of new addition
11/9
• Complete demolition of exterior basement walls
• Demolition/Tear out for new entrances
• Begin backfill of new addition and 1/2 of new parking lot
• Begin underground ductwork at new addition
• Begin underground electrical conduit at new addition
• Form/pour exterior walls of new addition
• Form/pour slab on grade for underground ductwork
• Demolition at existing elevator shaft (lower level)



- October 2008
10/19
Inside:
• Saw-cut floor in lower-level east men's bathrooms and electrical room.
• Lower level re-plumbing.
• Demolition of old duct work and laying out new duct work.
Outside:
• Demolition of outside walls for doorways and hallway in lower level
• Foundation poured for walls of gathering space area.
• Footings placed in former west atrium area.
• Utility poles to be removed.
10/12
Inside
• Plumbers rerouting and installing new pipe.
• Continued demolition in east lower level.
• Verizon to switch over service lines.
• Insulation of the Nave completed.
Outside
• Switch-over of transformer.
• Third well will be drilled in the southeast corner of the lot.
• Demolition of asphalt and concrete will continue.
• Forming the elevator pit walls.
10/5
• Excavation for new elevator.
• Footings to be placed in former east atrium area.
• Shutting down and dismantling the chiller.
• Starting sanitary connection to Fairfield Avenue.
• New piping in lower-level continues. 
- September 2008 — Demolition Work Continues...
9/28
• Installation of the sanitary and storm drains continues.
• Demolition of the east atrium and foundation completed.
• Verizon continues underground work.
• Waiting on delivery of new transformer.
• Excavating for new elevator begins.
• STS Security onsite during worship services and evening events.
9/21
• Drilling of the #2 well has begun
• The old heating piping is being removed from the east wing
9/1-9/14
Atrium:
• Preparation for demolition starts Sept. 12.
• Two exits (kitchen and the door next to the old receptionist office) boarded up, with no exit access.
• All remaining doors are within fire route regulations per the Fire Marshal inspection of fire routes.
West Wing:
• West Wing lower level restrooms remain accessible.
Lower Level:
• Access to the lower level is from West Wing stairs only. The plastic sheeting has been hung o minimize dust.
• Demolition has taken place in the Youth Center, YCC, TCC, Brides Room, Men’s restroom.
• Pastor Frazier's office will move temporarily to the office next to Pastor Fugate.
Exterior:
Exterior signage, pending updated construction images and city approval, will go up on the surrounding fence to help both Trinity members and the community know more about the project.
- SeptemberFest 2008
Vic Martin updated Trinity members and friends on the "Seeds of Faith" building project at SeptemberFest. He shared new progress drawings, as well as tentative construction timeline updates.

- August 2008 — Construction begins!
The fence is up and utility and preliminary prep work have begun! The area behind Trinity, the alley, and the parking lot at Washington and Ewing will remain inaccessible due to the construction for the "Seeds of Faith" capital campaign project.
To enter the church:
Please use the Fairfield (Education Wing) entrance into the building Monday through Sunday. The Fairfield and Wayne Street entrances will be open on Sundays.
To park when visiting Trinity:
Those coming to Trinity should park in Trinity's Wayne and Fairfield lot. Spaces will be reserved in the front of the church for those who have mobility challenges. A Trinity parking sticker is needed to park in Trinity's parking lot during the week, but not on Sundays. Please get your sticker at the receptionist's desk (now located in the education office).
If you have any concerns or need assistance to enter the building, please call the church before you leave home, and someone will be available to meet you and assist you.